Project Management and Business Reporting Tools
HOME   • PRODUCTS   • BUY   • DOWNLOAD   • SUPPORT   • CONTACT Computer Systems Odessa
Project Management and Business Reporting Tools
Project Management and Business Reporting Tools
Project Planning
blunk
blunk
blunk
blunk
blunk
blunk
blunk






Free TRIAL
blunk
blunkDownload Free Trial of ConceptDraw Project by clicking the icon
blunkMacintoshWindows
blunk
blunk


Todays offer
blunk
blunkBuy ConceptDraw Business Suite and save 250$ !
blunk
blunk


Other products
blunk
blunkProject manager bundle - Brainstorm ideas for your projects individually, develop project task lists.
blunk
blunk
Project Planning

Previous | Content | Next


Developing a project

Now we can move to project development. Switch to Gantt Chart mode: choose Gantt Chart in menu View.

A two-part window will appear: the left part of the window is a list of tasks with different parameters, the right one is a graphic representation of the left part, a Gantt Chart.

Add Task

To add a new task use Insert New Task in menu Tasks. To properly name the task you need to activate text edit mode. For this double-click on the task name and enter the name you mean. Do not forget to quit the text edit mode for saving the changes. For this just click on any task free display spot.

Task: Add the following tasks to the project:

  • Assign date
  • Make up the list of participants
  • Choose a place
  • Plan the picnic
  • Fix the budget
  • Buy food
  • Announce the time of the departure
  • Gather for the departure
  • Summarize

To add a subtask select a task and use Add New Subtask in menu Tasks.

Add to the task "Plan the picnic" the following subtasks:

  • Make up entertainment list
  • Make up food list
  • Make up equipment list

Now we get the following list of tasks:

List of tasks

Assign plan dates

Now we’ll set Start and Finish dates and duration for each task:
To set a date, double-click on the cell with the date and choose the arrow on the right – a calendar will appear. Choose the necessary date in the calendar. To shift to the previous/following month use the right and left arrows.

Choose the necessary date Date

You need to specify just Start and either of the parameters left – Finish or Duration, the third one will be defined by the program automatically.

Task: Set the following dates for task fulfillment:

  • Set the date: 08/02/04 – 08/02/04, 1day
  • Choose a place: 08/02/04 – 08/04/04, 3 days
  • Make up the list of participants: 08/04/04 – 08/06/04, 3 days
  • Plan the picnic
    • Make up entertainment list: 08/09/04 – 08/11/04, 3 days
    • Make up food list: 08/09/04 – 08/13/04, 5 days
    • Make up equipment list: 08/12/04 – 08/12/04, 1day
  • Fix the budget: 08/16/04 – 08/16/04, 1 day
  • Buy food: 08/19/04 – 08/20/04, 2 days
  • Announce the time of departure: 08/19/04 – 08/19/04, 1day
  • Gather for the departure: 08/20/04 – 08/20/04, 1day
  • Summarize: 08/23/04 – 08/23/04, 1day

The time of task fulfillment is defined by the program automatically.

The time of task fulfillment

Deadlines

Deadlines are set for the tasks fulfillment time of which cannot be put off. For details see Deadlines in Lesson 2.

Tasks with no deadline set in the Deadline column are marked NA – not available. To set a deadline for a task, you need:
1. Select a task
2. Use Deadline in menu Tasks

Task: Set the deadline for the task "Choose a place".

Deadline for the task


Previous | Content | Next



blunk
ConceptDraw Project  • Project Manager Bundle  • Business Suite  • Documentation Suite
Home Buy Products Download Support Contact Site Map
Copyright® 2008 Computer Systems Odessa corp. All rights reserved.