Project Management and Business Reporting Tools
Project Management and Business Reporting Tools
Project Planning
blunk
blunk
blunk
blunk
blunk
blunk
blunk






Free TRIAL
blunk
blunkDownload Free Trial of ConceptDraw Project by clicking the icon
blunkMacintoshWindows
blunk
blunk


Todays offer
blunk
blunkBuy ConceptDraw Business Suite and save 250$ !
blunk
blunk


Other products
blunk
blunkProject manager bundle - Brainstorm ideas for your projects individually, develop project task lists.
blunk
blunk
Project Planning

Previous | Content | Next


Intertask dependencies

Intertask dependencies can be of 4 types:

  • finish to start – the most common link type indicating that task Y cannot be started, until task X has been finished
  • finish to finish – task Y cannot be finished, until task X has been finished
  • start to finish – task Y cannot be finished, until task X has been started
  • start to start – task Y cannot be started, until task X has been started

To assign the most common link type, finish to start, select the tasks first you’d like to assign links to: for this, select one task and then pressing Ctrl button select another task. Then use one of the following:

  1. Use Link Tasks in menu Workspace.
  2. Use Link Tasks button on the toolbar Workspace.

Any link type can be assigned in the dialog Task Information, on the Predecessors tab. For this do the following:

  1. Select dependant task.
  2. Then use Predecessors in menu Tasks.
  3. To add a new link press New button. A new row will be added with the name of the task from which goes the link, with the link type and with minimum interval between tasks.
    A new row will be 
    added with the name of the task from which goes the link
    A new row will be 
    added with the name of the task from which goes the link

 

Note: In Lag graph minim interval is indicated between:

  • finish to start – the end of task X and the beginning of task Y.
  • finish to finish – the end of task Y and the end of task X.
  • start to finish – the beginning of task X and the end of task Y.
  • start to start – the beginning of task Y and the beginning of task X.
  1. To select a task from which goes the link, double-click on the cell with the task and then select the needed task from the pop up menu.
  2. Task form Task form
  3. To select a link type, double-click on the corresponding cell and select the needed type from the pop up menu.
    Link tipe Link tipe
  4. To select minimum time interval, double-click on the corresponding cell and with the help of the arrows indicate the needed length. Time interval can be set in various measurements from minutes to weeks. For this in the cell Lag specify the needed measurements:
  • m - minutes
  • h - hours
  • d - days
  • w - weeks
    Time interval Time interval
Task information: Predecessors
Task information: Predecessors

Do not forget to press OK, to save the changes.

Task: In our example, let’s add finish to start link type between the tasks "Make up food list" and "Buy food" and also between the tasks "Make up equipment list" and "Buy lacking equipment".

Links between tasks can be removed the same way (use one of the methods given below):

  1. Select the tasks to be independent. For this select one task and then, pressing Ctrl button, select another task. Then use one of the following steps:
    1. Use Unlink Tasks in menu Workspace.
    2. Use Unlink Tasks button on the toolbar Workspace.
  2. Select the task to be linked. Then use Predecessors in menu Tasks. Select the link to be deleted and press Delete.

Do not forget to press OK, to save the changes.


Previous | Content | Next



blunk
ConceptDraw Project  • Project Manager Bundle  • Business Suite  • Documentation Suite
Home Buy Products Download Support Contact Site Map
Copyright® 2008 Computer Systems Odessa corp. All rights reserved.