Project Management and Business Reporting Tools
HOME   • PRODUCTS   • BUY   • DOWNLOAD   • SUPPORT   • CONTACT Computer Systems Odessa
Project Management and Business Reporting Tools
Project Management and Business Reporting Tools
Project Planning
blunk
blunk
blunk
blunk
blunk
blunk
blunk






Free TRIAL
blunk
blunkDownload Free Trial of ConceptDraw Project by clicking the icon
blunkMacintoshWindows
blunk
blunk


Todays offer
blunk
blunkBuy ConceptDraw Business Suite and save 250$ !
blunk
blunk


Other products
blunk
blunkProject manager bundle - Brainstorm ideas for your projects individually, develop project task lists.
blunk
blunk
Project Planning

Previous | Content | Next


Milestones. Deadlines

Milestones

Important components of the project which help to control time of task completion are milestones and deadlines.

Milestone is a task, crowning an important part of the project. Milestones are indicators of key points of the project. Without reaching them another series of tasks cannot be started. Milestones are often final tasks of project phases. On the graphic part of the diagram they are marked by .

Changing a task into a milestone can be done by the following steps (do not forget to select the task first!):

  1. Use Milestone in menu Tasks.
  2. Call the context menu of the task and use Milestone.

In both cases Milestone command will be marked in menu, indicating that the given task is a milestone.

Milestone Milestone
  1. Call dialog Task Information in menu Tasks or in the task context menu and check option Milestone in section Info. Closing the dialog, do not forget to press OK, to save changes.
Task information
Task information

To remove milestone status from the task, select the command again and the mark will disappear.

Task: In our example there can be such a task as "Fix the budget" . In fact, this task splits the project in two parts: planning phase and completing phase, as before fixing the budget we realized our actions only on paper and we then switch to their implementation. Let’s give it Milestone status by one of the mentioned above methods.

Giving Milestone 
  status by one of the mentioned above methods.

Deadlines

Deadline is the last date the task can be completed. During the process of project completion a necessity can occur to correct time of completion for some of the tasks. However, postponing of some completion times is extremely undesirable. For instance, if the completion time for some task has been fixed in the contact. Or the beginning of the work of the whole team whose members are involved in other projects depends on the task. Not completing the task on term in this case may result in very undesirable consequences – fines, canceling the contract, non-completion of a whole set of projects. If such a task fails to be completed in time, then instead of postponing the deadline, you better trying to meet the deadline, using additional means, for instance, by providing additional resources to it or by relieving the doers of any other work.

To mark such an important task on the project its deadline is specified. At that, the deadline must not necessarily coincide with the Finish Date – it can be assigned to a later time. On the project the deadline is marked .

Assigning the deadline for a task can be done by the following ways (do not forget to select the task first!):

  1. Use Deadline in menu Tasks.
  2. Call the task context menu and use Deadline.

In both cases Deadline command will be marked in menu, indicating that the deadline has been specified for the task.

Deadline Deadline

Note: the deadline must not necessarily coincide with the Finish Date of the task it can be assigned later. But setting the deadline which does not coincide with the task Finish Date, can be done by the third method in Task Information.

  1. Call the dialog Task Information in Tasks, in the task context menu or its graphic representation and mark Deadline option it in section Dates. Closing the dialog, do not forget to press OK, to save changes.
Task information
Task information

To remove the deadline from a task, select the command again and the mark will disappear.

Task: In our example such critical tasks are those preceding the trip, as not completing those in time will force the trip itself to be postponed. Let’s set the deadline for all tasks – August, 20.
Let’s assign the deadline for the task "Buy food" by any of the described above methods, and for the tasks "Hire a bus to take people there and back" and "Buy lacking equipment" via dialog Task Information.

Deadline for the task


Previous | Content | Next



blunk
ConceptDraw Project  • Project Manager Bundle  • Business Suite  • Documentation Suite
Home Buy Products Download Support Contact Site Map
Copyright® 2008 Computer Systems Odessa corp. All rights reserved.