Highlight report

Highlight reports should be prepared by the project manager at intervals determined by the project owner, often monthly or four-weekly. They can also be generated at any time if the project manager becomes aware of an issue of sufficient urgency that needs to be communicated to the project owner. Highlight reports are also used to collate and distil the information conveyed in the progress reports. They review progress to date and highlight any actual or potential problems which have been identified during the period which they cover.